Alignment & delivery

Value stream mapping

Every step from idea to production, with the waiting time between them.

When. Teams optimise the steps they can see. The time is almost always lost in the queues between them, which nobody owns.

Duration
3 h
Participants
Everyone who touches the stream, including outside the team
Output
The real lead time, and where it is actually spent
Stage
Post-PMF · Scale-up · Mature
IdeaRefinedIn buildIn reviewIn product…
Find the right sequence

In FigJam: File → Duplicate to your drafts, then keep this workshop's section. Get the file on Figma Community

Filled example

IdeaWork: 2 h to writethe itemWait: 11 days beforeit is refinedRefinedWork: 1 h in TuesdayrefinementWait: 6 days waitingfor a sprintboundaryIn buildWork: 3 days ofactual buildWait: 1 day waitingfor a design answerIn reviewWork: 40 min ofreviewWait: 4 days, Tom isthe only reviewerfor sync codeIn productionWork: 30 min toreleaseWait: 3 days, norelease on a FridayWait time between stepsTotal lead time: 28daysTotal working time:3.5 daysWorking share: 12 %

Example data. Fieldnote is a fictional company used to fill every board, so the examples tell one consistent story.

Fieldnote, mapping the last ten shipped items from idea to production, with Karim, Tom, Ana and Julien. Real dates pulled from the tracker.

What the team took away

The team was about to hire to go faster. Twelve percent working time said the problem was the 11 days before refinement and the single reviewer, neither of which a new hire would fix.

How to run it

Preparation

Agenda

  1. 30 min
    Draw the steps
    List every step from idea to production, including approvals and handoffs. Do not judge anything yet, just get the boxes on the wall.
  2. 40 min
    Add the two times
    For each step, the time spent working on it, and the time spent waiting before it. The second number is the one nobody has ever measured.
  3. 20 min
    Compute the ratio
    Add up both columns. The share of working time in total lead time is usually under fifteen percent, and saying that number out loud changes the conversation.
  4. 30 min
    Find the biggest queue
    Point at the longest wait, not the slowest step. Ask who owns it, and what it is waiting for.
  5. 30 min
    One experiment
    Pick one queue and design one change to shrink it. One, measurable, with a date to re-measure the lead time.

Pitfalls

Afterwards

Re-measure the lead time after one cycle with the change in place. If the biggest queue is a cross-team dependency, the dependency map is the next session.

Source : https://www.lean.org/lexicon-terms/value-stream-mapping/