Alignment & delivery

Team board

One team's iterations laid out side by side, with its items, its dependencies and its objectives.

When. The program board shows what crosses teams. The team board shows whether a single team can actually hold its commitment.

Duration
2 h
Participants
One team, during big-room planning
Output
An iteration plan the team commits to out loud
Stage
Post-PMF · Scale-up · Mature
ItemsDependenciesMilestonesObjectivesIteration 1Iteration 2Iteration 3Iteration 4Iteration 5
Find the right sequence

In FigJam: File → Duplicate to your drafts, then keep this workshop's section. Get the file on Figma Community

Filled example

ItemsDependenciesMilestonesObjectivesIteration 1Iteration 2Iteration 3Iteration 4Iteration 5skip companyprofile, removesecond confirmationnoneactivation funnelinstrumentedfirst hour of usemeasurableSMS invite, pre-fillfirst jobOffice web for theinvite endpoint, dueday 4nonetechniciansreachable withoutemailoffline draft, partoneTom's conflictdecision, due beforestartnonenothing typed islostoffline draft, parttwo and sync alertssupport tooling fromJulieninternal release to5 pilot companiesnothing typed islostbuffer, deliberatelyhalf emptynonequarter reviewabsorb whatiterations 3 and 4overrun

Example data. Fieldnote is a fictional company used to fill every board, so the examples tell one consistent story.

Fieldnote, Field app squad planning its quarter alongside Office web and the new Integrations squad. Capacity cut by the August holidays.

What the team took away

The squad kept iteration 5 half empty on purpose after three quarters of carrying work over. The August capacity cut was written before any item was placed, which is why iteration 3 only got half a feature.

How to run it

Preparation

Agenda

  1. 20 min
    Capacity first
    Write the real capacity per iteration before any item is placed. Planning first and checking capacity later always produces a plan that fits on paper.
  2. 45 min
    Place the items
    Put items in iterations, respecting order and dependencies. When a column is full, stop: the overflow is the conversation you came for.
  3. 30 min
    Draw the dependencies
    Every item that needs another team gets a string to it, with a date. A dependency with no date is a hope.
  4. 25 min
    Write the objectives
    Turn the plan into two or three objectives in business language, not item titles. These are what you will be judged on, not the board.
  5. 20 min
    Say the risks out loud
    Name what could stop this plan, and send each risk to the ROAM board rather than solving it here.
  6. 10 min
    Commit, with a number
    The team votes confidence on its own plan. Under a certain threshold, you replan now rather than discovering it in three weeks.

Pitfalls

Afterwards

The dependencies go on the program board, the risks go to ROAM. Revisit the board at each iteration boundary: an untouched team board is a plan nobody is using.

Source : https://scaledagileframework.com/pi-planning/