Alignment & delivery

PI Planning (SAFe)

Two days where all the teams of the train plan the increment, expose their dependencies and commit.

When. Past four or five teams on the same product, a formal quarterly synchronisation becomes necessary.

Duration
2 d
Participants
All teams of the train
Output
PI objectives + program board
Stage
Scale-up · Mature
Sprint 1Sprint 2Sprint 3Sprint 4Sprint 5IPTeam 1Team 2Team 3Team 4Milestones
Open in FigJamFind the right sequence

In FigJam: File → Duplicate to your drafts, then keep this workshop's section. Get the file on Figma Community

Filled example

Sprint 1Sprint 2Sprint 3Sprint 4Sprint 5IPTeam 1Team 2Team 3Team 4Milestonesguidedfirst-interventionflowoffline queue forphotosoffline sync v1parts scan spikeoffline synchardeningbuffer + demo prepTeam 1 = Field apponboarding checklistfor dispatchersinvite techniciansby SMSdispatch API v2invoicing status onjob cardactivation dashboardfor Sophiebug bashTeam 2 = Office webPennylane OAuthcustomer accountmappingpush invoicesnightlyerror retry andalertsbeta with 12companiesdocs + supporthandoverTeam 3 =Integrationsactivation events inwarehousechurn cohorts byintegration statusweekly activationreportsync error dashboardPI metrics readoutretro dataTeam 4 = Data20 new companies onguided onboardingdispatch API v2unblocks offlinePennylane beta livetime-to-10 measuredon the whole PI

Example data. Fieldnote is a fictional company used to fill all 61 boards, so the examples tell one consistent story.

Scale-up Fieldnote, first PI Planning with four teams (Field app, Office web, Integrations, Data) and the quarter objective: cut time-to-first-10-interventions from 14 days to 5.

What the team took away

Three red strings all point at dispatch API v2 in sprint 3; Office web moves it to sprint 2 and pushes SMS invites out one sprint. Confidence vote: 4 out of 5 on average.

How to run it

Preparation

Agenda

  1. 180 min
    Day 1 morning: context
    Business context by a business owner (20 min), product vision and top features by product management (45 min), architecture vision (30 min), planning rules and capacity (20 min). Questions after each block, not during.
  2. 240 min
    Day 1 afternoon: team breakouts, draft 1
    Each team drafts its sprint plan, writes PI objectives, and posts features and dependencies on the program board. Scrum masters walk between teams to flag conflicts early.
  3. 60 min
    Day 1 close: draft review
    Each team presents its draft in 5 minutes: objectives, risks, dependencies. Business owners note what they will challenge tomorrow.
  4. 210 min
    Day 2 morning: adjustments, draft 2
    Management shares overnight decisions on scope and capacity. Teams rework their plans and resolve dependencies face to face with the other team, not by proxy.
  5. 90 min
    Day 2 afternoon: final plans and business value
    Each team presents its final plan. Business owners assign business value 1 to 10 to every PI objective, out loud, in front of the team.
  6. 60 min
    Risks and confidence vote
    Every program risk is ROAMed: resolved, owned, accepted, mitigated. Then fist of five per team. Any team at 2 or below reworks its plan before leaving.

Pitfalls

Afterwards

PI objectives and the program board are the contract for the increment. The RTE keeps the board alive in the weekly sync; the Inspect & Adapt at the end of the PI closes the loop.